The Accra Metropolitan Assembly (AMA), in collaboration with The Or Foundation and the Kantamanto Obroni Wawu Business Association (KOBA), has commenced a major desilting exercise on the Okaikwei Road storm drain in Kantamanto to address persistent flooding and improve sanitation in the area.
The exercise, which began over the weekend and is currently ongoing, forms part of a broader effort to enhance urban resilience in one of Accra’s busiest commercial hubs.
Approximately 154 waste workers drawn from Tide Turners and the June 4 Task Force were deployed for the operation, entering the underground drain system through newly created access points to remove accumulated waste.
Over 12 hours at the start of the exercise, the team cleared approximately 400 metres of the heavily silted drain, removing large volumes of plastic, silt, and textile waste. With 60 tonnes already cleared, an estimated 120 tonnes more are expected to be removed as work continues.


The storm drain, which stretches from Tema Station through Okai Kwei Road to the June 4 Market and into the Korle Lagoon, had reportedly not been desilted since its construction, resulting in severe blockages and frequent flooding, even after short rainfall events.
Speaking to the media, the Mayor of Accra, Hon. Michael Kpakpo Allotey emphasised that the AMA would continue to collaborate with stakeholders to strengthen drainage systems, improve sanitation and build a more resilient and flood-resistant city.
Head of Waste Management at the AMA, Engineer Solomon Noi, explained that the enclosed nature of the drain, which was originally designed with minimal access points, had made maintenance difficult over the years.