Work on the rehabilitation of the 111 kilometre Mankessim, Ajumako and Agona Swedru road corridor has reached 15% completion, with construction activities progressing steadily since work began in January 2026.
The project, which is expected to be completed by January 2028, forms part of efforts to improve road connectivity and support economic development across the Central Region.
According to project officials, the contractor is currently carrying out site clearance, demolition works, earthworks and the construction of drainage structures. So far, 22 culverts of various sizes have been completed along the route.
The scope of the project includes pavement works, asphalt surfacing, drainage infrastructure, road furniture and street lighting. Three hydraulic bridges are also being constructed at Barfikrom and Ochiso to improve accessibility and enhance traffic flow.
When completed, the road is expected to provide a critical link between the N4 Highway and the Coastal Corridor on the N1 as well as the Central Corridors on the N6 and N8 highways.
Officials say the upgraded road will improve the movement of people, goods and services across the Central Region and beyond, while supporting economic activities in the districts of Agona, Gomoa, Ajumako Enyan Essiam, Mfantsiman and Asikuma Odobeng Brakwa.
The project is also expected to strengthen regional integration and contribute to broader socio economic development by improving access to markets, businesses and essential services.