US$200 million was borrowed to build 5,000 homes. Years later, only 1,506 units were standing – most of them incomplete. Where did the money go?
That question is at the centre of renewed scrutiny over the Saglemi Affordable Housing Project.
Speaking on Metro TV’s Home Owners Show, Elvis Darko, Founder and Editor of The NewsCenta newspaper, questioned how a project approved for 5,000 housing units delivered far fewer units despite almost the entire loan being expended.
According to Darko’s review of parliamentary and project documents, the $200 million facility, including interest, was expected to deliver 5,000 units through a structured financing arrangement.
However, only about 1,506 units were constructed, with just around 650 having some of the required fittings. He said a state assessment valued the work done at significantly less than the amount spent.
The project subsequently became the subject of investigations and prosecution over alleged financial irregularities.
But Desmond Darko, Editor of The Catalyst, says the controversy should not be reduced to a single administration.
He argues that even if there were questions about the use of funds, the decision to abandon the project created a second problem, exposing the site to vandalism and further deterioration.
Both commentators are calling for accountability, while insisting that the probe into the project’s finances should not prevent the completion of housing that is urgently needed.
By: Kemi Keys